Tbilisi (GBC) – The U.S. District Court for the District of Columbia has enforced an International Chamber of Commerce (ICC) arbitration award requiring Georgia to pay $383 million in compensation to the Turkish company ENKA. Including accrued interest, the total amount payable has already exceeded $400 million.

According to the news agency haqqin.az, this information is revealed in the case files of the U.S. District Court for the District of Columbia (*ENKA Renewables LLC v. Georgia*).

The International Chamber of Commerce issued the arbitration award in December 2024. Interest on the amount accrues on a quarterly basis.

The arbitration dispute began in October 2021, after then-Prime Minister Irakli Garibashvili announced that the Namakhvani HPP project would not proceed in its existing form.

By that time, ENKA had invested approximately $100 million in preparatory work for the project. The total value of the project had been estimated at $800 million.